IT carve-out: the 8 most common mistakes – and how to avoid them

A carve-out rarely fails because of strategy or the purchase price. It fails because of the complexity, duration and cost of the separation – and no area is affected more strongly than IT. Applications, licenses, data and processes have been interwoven across the group for years; a contract clause alone does not untangle them. I have led IT M&A at an international automotive supplier group for more than fifteen years and was responsible for more than 100 international projects covering due diligence, carve-out, integration and Transition Services Agreements (TSAs). The same eight mistakes keep reappearing. We describe them here together with the countermeasures that have proven their worth in practice. This article is deliberately practice-oriented and does not constitute legal advice; consult your advisors on contractual matters.

Mistake 1: TSA negotiations start too late

Many deal teams concentrate on the purchase agreement and the valuation. The TSA is treated as a detail and is negotiated only between signing and closing – at a stage when time and negotiating room are lacking. But the seller is not a service provider: whoever defines services, exclusions and pricing mechanisms late pays for it after closing.

Countermeasure: We start TSA negotiations as early as practically possible in the deal cycle – ideally in parallel with due diligence. Even in the bidding process, dependable TSA commitments should be made, and the people who will actually deliver the services sit at the table from the start. That reduces bidder uncertainty and improves the quality of the offers.

Mistake 2: Unclear perimeter and unclear scope

When legal, tax, finance, HR and IT have different ideas about what belongs to the new company, gaps appear: assets without a clear assignment, rights in the wrong legal entity, systems nobody planned for. The buyer finds this in due diligence – and adjusts the price.

Countermeasure: We define the perimeter before pricing, in a documented separation concept: which systems, data, contracts and employees transfer, which stay, which are separated. Every function confirms its share in writing. For data, a tight classification has proven its worth: what transfers in full, what is reduced or anonymized, what remains locked. The business decides the scope, not IT; IT owns the how.

Mistake 3: Change-of-control clauses are overlooked

Numerous supply and license agreements contain clauses that become terminable on a change of ownership or require consent. Software is often licensed for internal use only; a transfer to the new company needs the vendor’s consent. In larger transactions this can mean hundreds of consents – each one with negotiations and fees. Whoever discovers this only after signing puts the ability to operate at all on day one at risk.

Countermeasure: We screen the contract inventory for change-of-control clauses and consent requirements before the valuation model is final. Settled early: who identifies the consents, who obtains them, who carries the costs – and what happens if a vendor refuses. It has proven effective to give both parties a financial stake in the consent process; that keeps the process moving.

Mistake 4: Wrong TSA timelines

Timelines that are too short create operational bottlenecks precisely when the new company is at its most vulnerable. Timelines that are too long tie the seller to structures it wants to dissolve and make the transition phase more expensive. Often the buyer simply does not know its actual need.

Countermeasure: We do not derive TSA timelines from negotiation outcomes but from the migration plan: a realistic end date per service, derived from staff availability, vendor lead times and the dependencies between the individual migrations. Extension options remain limited, with defined notice periods and, where appropriate, adjusted prices. Service levels are set so that operations remain sustainable – not so that the agreement looks good.

Mistake 5: The target operating model is missing

Without a picture of the target state, the carve-out becomes a repair operation: what is inconvenient gets separated instead of building an IT that can stand on its own. The results are transitional solutions that become permanent, and a new company that cannot act strategically.

Countermeasure: Before signing, we answer the question of whether the business can exist on its own – from what point, at what cost, with which dependencies. From that, a target architecture with standards and priorities emerges. Not every legacy system has to be replaced immediately: we assess dependencies by business impact, prioritize with a simple scoring grid and migrate step by step instead of all at once.

Mistake 6: System and data documentation is incomplete

Undocumented procedures, outdated infrastructure, unknown data flows: whatever due diligence does not find, the project team finds later – at a high price. The buyer inherits technical debt and dependencies on individual vendors, whose reduction is neither planned nor priced in.

Countermeasure: In the IT due diligence we build a complete inventory: applications, interfaces, licenses, vendor dependencies and known technical debt – transparently aligned between IT, legal, procurement and compliance. For the data handover, a simple procedure has proven itself: every transfer is described as a one-page request, approved by the responsible business owner and assigned to a category. A checksum at the handover later ends any dispute about what was actually delivered.

Mistake 7: Legal, tax, finance and IT work in silos

Carve-outs are cross-functional undertakings. When the workstreams plan separately, contradictions arise: the financial model builds on assumptions that cannot be implemented legally; local contracts and government approvals are treated as secondary and jeopardize the timetable.

Countermeasure: We involve all workstreams in an interlocked way from the beginning – not in parallel, but integrated. The legal feasibility of the commercial assumptions is tested before the valuation is final. Fixed joint dates, a consistent data room and coordinated documents between the main agreement and local contracts prevent the contradictions that lead to disputes after closing.

Mistake 8: There is no exit plan for the end of the TSA

The TSA is concluded, but its end is not planned. What happens after the separation – who cleans up which data, which transitional solutions are decommissioned, how contracts end – is then settled in conflict. Missing exit rules and unclear responsibilities practically invite disputes.

Countermeasure: We plan the TSA exit from the first negotiation onward: an exit criterion and an owner per service, milestones that include the decommissioning of temporary solutions, and a fixed body that decides on open points. The contract inventory is also reviewed for exit options – agreed data portability and exit rights secure the new company’s independence for the long term.

Conclusion: carve-out mistakes are almost always planning mistakes

All eight mistakes trace back to one cause: planning starts too late and too isolated. Whoever thinks through perimeter, target operating model, data handover and TSA exit before signing negotiates from a position of clarity – and brings the new company quickly and lastingly into standalone operational readiness.

We support companies with IT due diligence, carve-out planning and TSA design – building on my experience from more than 100 international projects. If you are preparing a transaction or are in the middle of a separation: get in touch via www.hauser-digital.de/en/contact/.